Restaurant opening and holiday uniform timeline

Standard turnaround at Battle Born Clothing is 28 days from proof approval. Add time for sizes, proofs and shipping and the real answer is: order seven to eight weeks before you need uniforms on bodies. Here is the schedule.

The clock starts at proof approval, not at the quote

Quotes usually go out the same business day. The 28 days start when you approve the digital proof. Days spent collecting sizes or revising artwork are on your side of the line, so the fastest orders are the ones that arrive with a clean logo and a finished roster.

Week-by-week for a new opening

Working back from opening day
Weeks before openingWhat happens
8Send logo, position list and estimated counts on the quote form. Quote same business day.
7Finalize the roster and sizes. Approve the proof. The 28-day clock starts.
6 to 4Blanks ordered from SanMar Reno or S&S; digitizing and screens made; production.
3Order ships. Allow a week for ground shipping across the country.
2Uniforms arrive. Hand out, check sizes, note any gaps.
1Place a small top-up for new hires if needed (priced at the 12-23 tier).
0Open.

Holiday season

Holiday staffing peaks from mid-November through New Year's. Suppliers also get busy, and blank stock in popular colors thins out. Order by the end of September to have uniforms by early November without a rush charge.

Holiday schedule
DateAction
By Sept 30Quote and proof approved
Late OctoberOrder ships
Early NovemberUniforms on seasonal hires
After Oct 1Rush quoted per job; we will tell you what is realistic

What slows orders down

What speeds them up

Seasonal patios and summer hires

Patio season brings the same crunch as the holidays on a smaller scale. If you add 10 servers every May, order their aprons and hats in March. Aprons and hats need no sizes, so you can order the whole summer set before you have hired anyone. Beanies for winter door staff follow the same logic in reverse: order in September.

Rebrands

A rebrand is an opening without the construction delays. The step most people skip is the proof: new logos often have fine detail that needs simplifying for embroidery, and that back-and-forth is faster before the proof than after. Send the new vector files as soon as the designer finalizes them, even before you know the counts, so digitizing can start. Then send the roster when it is ready.

Rush

Rush is quoted per job, not from a chart. Tell us the real date on the quote form and what you need first. Often the aprons and hats can go ahead while the sized pieces follow.

Get a quote

Questions

How long does a reorder take?

The same 28 days from proof approval as a standard order, though reorders skip digitizing and the proof is usually approved the same day.

Can we get part of the order early?

Ask. A split ship is quoted per job and usually practical for no-size pieces like aprons and hats.

Do you ship to a new location before it opens?

Yes, to any US address you give us. Make sure someone is there to receive it.